—— COFNII STANDARDS OVERVIEW

How the main generic-cabling standards work together.

ISO/IEC 11801 and BS EN 50173 describe the cabling system and the performance it must provide. BS EN 50174 explains how that system should be specified, planned, installed and quality-assured.

INTERNATIONAL MODEL

ISO/IEC 11801

UK & EUROPEAN SERIES

BS EN 50173

INSTALLATION SERIES

BS EN 50174

ESSENTIAL COMPANIONS

BS EN 50346 & 50310

Edition check · August 2026

Standards are reviewed and amended. BSI currently lists key 2018 editions as current or under review, and revision work is active. Always cite the exact part, edition and amendments in the project specification.

—— THE SHORT EXPLANATION —

Three families. Two different jobs.

01 · International

ISO/IEC 11801

What should the generic cabling system be capable of?

The international family establishes common generic-cabling structures, performance concepts and premises-specific requirements for customer premises.

02 - UK ADOPTION OF THE EUROPEAN SERIES

BS EN 50173

What system and performance should be provided in each type of premises?

This is the British adoption of the EN 50173 family. Its parts cover general, office, industrial, residential, data-centre and distributed-building-services cabling.

03 - INSTALLATION

BS EN 50174

How should the installation be specified, delivered and assured?

This family deals with installation specifications, quality assurance, documentation and practical planning and installation inside and outside buildings.

—— PART BY PART MAPPING

ISO/IEC 11801 and BS EN 50173 follow a parallel structure.

Choose the general requirements and the premises-specific part relevant to the project. Mixed-use sites may require more than one part.

ENVIRONMENT
INTERNATIONAL
UK / EUROPEAN
IN SHORT
Data centres
ISO/IEC 11801-5
BS EN 50173-5
Generic balanced-copper and optical-fibre cabling within computer-room and data-centre spaces.
Distributed building services
ISO/IEC 11801-6
BS EN 50173-6
Generic cabling supporting distributed services such as wireless access points, building controls, security devices and other networked building systems.
Homes
ISO/IEC 11801-4
BS EN 50173-4
Generic cabling in homes for information and communications technology and related residential services.
Industrial premises
ISO/IEC 11801-3
BS EN 50173-3
Generic cabling for industrial spaces, including the environmental and topology considerations associated with automation areas.
General requirements
ISO/IEC 11801-1
BS EN 50173-1
The common architecture, link and channel performance concepts, component requirements and conformance framework used by the other premises-specific parts.
Office premises
ISO/IEC 11801-2
BS EN 50173-2
Generic balanced-copper and optical-fibre cabling within office premises and office areas in other buildings.

Closely aligned does not mean interchangeable. Differences in regional adoption, amendments, terminology and contractual wording must be checked against the authorised publications.

—— WIDER CROSS-REFERENCE

ISO/IEC 11801 and BS EN 50173 follow a parallel structure.

Choose the general requirements and the premises-specific part relevant to the project. Mixed-use sites may require more than one part.

SUBJECT
UK / EUROPE
INTERNATIONAL
COMPARABLE NORTH AMERICAN FAMILY
Bonding and telecommunications earthing
BS EN 50310
ISO/IEC 30129
ANSI/TIA-607 series
General customer-premises cabling
BS EN 50173-1
ISO/IEC 11801-1
ANSI/TIA-568 series
Office / commercial premises
BS EN 50173-2
ISO/IEC 11801-2
ANSI/TIA-568.1 series
Industrial premises
BS EN 50173-3
ISO/IEC 11801-3
ANSI/TIA-1005 series
Homes / residential premises
BS EN 50173-4
ISO/IEC 11801-4
ANSI/TIA-570 series
Data centres
BS EN 50173-5
ISO/IEC 11801-5
ANSI/TIA-942 series
Distributed building services
BS EN 50173-6
ISO/IEC 11801-6
ANSI/TIA-862 series
Specification, QA and installation
BS EN 50174-1, -2 and -3
ISO/IEC 14763 series
ANSI/TIA-569 and TIA-758 series (related scope)
Testing installed cabling
BS EN 50346
ISO/IEC 14763 series and media-specific test standards
ANSI/TIA media-specific field-test standards

Closely aligned does not mean interchangeable. Differences in regional adoption, amendments, terminology and contractual wording must be checked against the authorised publications.

—— COPPER TERMINATION

T568A or T568B: why two assignments exist.

T568A and T568B are colour-code assignments for the eight-position modular interface. They use the same four pairs and deliver the same transmission performance; only the orange and green pair positions are exchanged.

ANSI/TIA pin/pair assignment

The preferred TIA assignment for backward compatibility with one-pair and two-pair USOC telephone wiring.

1 white/green

2 green

3 white/orange

6 orange

Blue remains on pins 4–5; brown remains on pins 7–8.

ANSI/TIA pin/pair assignment

Retained because it matches the earlier AT&T 258A assignment and became common across a large installed base.

1 white/orange

2 orange

3 white/green

6 green

Blue remains on pins 4–5; brown remains on pins 7–8.

COFNII practical rule

Follow the project specification first. On an existing site, continue its documented convention. If neither applies, COFNII recommends T568B as the documented default for consistency with the scheme commonly encountered in UK installations.

Do not mix schemes on a normal permanent link.

T568A at one end and T568B at the other creates a crossover arrangement. That was historically used for particular direct equipment connections, but it is not a substitute for consistent, documented horizontal-cabling termination.

—— BS EN 50174 IN SHORT

The installation and quality-assurance family.

The three parts move from project-wide specification and records to practical installation planning inside and outside buildings.

BS EN 50174-1

Specification and quality assurance

Define it, document it and prove it.

✓  Installation specification and responsibilities

✓  Quality planning, inspection and acceptance

✓  Documentation, administration and records

✓  Testing, handover, operation and maintenance arrangements

02 · Participation

Installation inside buildings

Plan and install it correctly indoors.

✓  Pathways, spaces and installation routes

✓  Installation practices for copper and optical fibre

✓  Segregation and interaction with other services

✓  Environment, remote powering and installation conditions

03 · Evidence

Installation outside buildings

Plan and install it correctly outdoors.

✓  External pathways, routes and structures

✓  Copper and optical-fibre installation practice

✓  Mechanical, ingress and climatic considerations

✓  Site-specific conditions and wide-area cabling routes

—— ESSENTIAL COMPANION STANDARDS

Testing proves the installation. Bonding supports safe, reliable operation.

These standards sit alongside BS EN 50173 and BS EN 50174. They address two areas that must be designed into the project rather than treated as an afterthought at handover.

BS EN 50346

Testing of installed cabling

Test it and record the evidence.

Provides procedures for testing the transmission performance of installed information-technology cabling, covering balanced copper and optical fibre. It supports acceptance testing, application verification and fault investigation.

Test parameters and appropriate methods

Test systems, equipment and interfaces

Calibration and measurement procedures

Interpretation and documentation of results

BS 6701

UK installation, operation and maintenance

Connect cabling practice to UK-specific requirements.

Adds UK requirements for telecommunications equipment and cabling, including matters beyond BS EN 50174 and links to UK electrical-installation requirements. It should be considered alongside the BS EN cabling series on UK projects.

UK-specific installation requirements

Operation, administration and maintenance

Coordination with BS 7671

Fire-performance requirements for telecoms cables

BS EN 50310

Telecommunications bonding networks

Bond it to support safety and performance.

Sets requirements and recommendations for telecommunications bonding networks in buildings and other structures, helping reduce electrical risk and provide a reliable signal reference for information-technology equipment and cabling

Bonding-network design and configuration

Connections between conductive elements

Coordination with protective bonding

EMI immunity and signal-reference considerations

BS 7671

Requirements for electrical installations

Coordinate data cabling safely with electrical services.

The IET Wiring Regulations govern the design, erection and verification of UK electrical installations. For cabling projects they are relevant to electrical safety, routing, segregation, earthing, bonding and interfaces with power circuits.

Electrical safety and protective measures

Segregation from power circuits

Earthing and bonding coordination

Power over Ethernet and ICT interfaces

Important:

BS EN 50346 describes how installed cabling is tested; the pass/fail limits are taken from the relevant cabling or application standard and the agreed project specification.

SEPARATION FROM POWER

There is no universal separation distance.

Specify it. Coordinate it. Inspect it.

Determine the project requirement from BS EN 50174-2, BS 6701 and BS 7671, taking account of circuit type, cable construction, containment, barriers, electromagnetic environment and the manufacturer's instructions.

ACCESS STANDARDS LEGITIMATELY

Explore BSI Membership

BSI Membership can provide standards-related support, updates and purchasing benefits. Membership does not itself include full access to every standard; check BSI's current terms and options.

—— APPLIED TOGETHER

A practical standards-led project workflow.

From the client requirement to a testable, documented and maintainable installation.

01

Define the requirement

Identify the premises, applications, capacity, availability, environment and client outcomes.

04

Plan routes, separation and bonding

Apply BS EN 50174-2 inside buildings, BS EN 50174-3 to external routes, BS EN 50310 to telecommunications bonding, and coordinate UK electrical requirements through BS 6701 and BS 7671.

02

Select the design standard

Use ISO/IEC 11801 or the relevant BS EN 50173 premises part to establish the generic-cabling design and performance requirements.

05

Install and inspect

Follow the project specification, manufacturer instructions and the applicable installation practices.

03

Write the installation specification

Use BS EN 50174-1 to state responsibilities, quality controls, documentation, testing and acceptance requirements.

06

Test and hand over

Use BS EN 50346 and the specified media test methods to verify the installed links or channels, then provide results, labelling, drawings, administration and exceptions.

These standards are central but not the whole specification.

—— IMPORTANT BOUNDARY

A compliant project may also need application, electrical, bonding, fire, product, safety, building and client-specific requirements.

01

Testing & acceptance

BS EN 50346 together with the specified cabling limits and applicable media test methods.

02

UK installation requirements

BS 6701 alongside BS EN 50174 for UK-specific installation, operation, administration and maintenance requirements.

03

Electrical separation & safety

BS 7671 coordinated with BS EN 50174-2 and BS 6701 for routing, segregation and safe interfaces with power services.

04

Bonding requirements

BS EN 50310 alongside applicable protective earthing, electrical-safety and bonding requirements.

05

Manufacturer systems

Product instructions, design rules, warranty conditions and approved test limits.

06

Application & client requirements

IEEE applications, fire and CPR requirements, availability, security, naming, acceptance and operational needs.

—— STANDARDS FAQ

Common questions, answered clearly.

COFNII member guidance will provide deeper technical briefings, checklists and specification templates.

—— MOVE THE INDUSTRY FORWARD

Turn standards into better specifications and better installations.

bottom of page